A shop works a 400-minute day.

A shop works a 400-minute day. A shop works a 400-minute day. The manager of the shop wants an output of 200 units per day for the assembly line that has the elemental tasks shown in the table. Do the following:d.Compute the balance delay for each rule. Which one yields the better set of assignments in this instance?(Omit the “%” sign in your response.) Balance delay: both part b and c are % TaskImmediatePredecessorTask Time (minutes)a-0.5ba1.4ca1.2da0.7eb, c0.5fd1.0ge0.4hg0.3if0.5je, i0.8kh, j0.9mk0.3