Project management ch 6 | Operations Management homework help

 

 

Which of the following represents an activity on an AON project network?
  A) An arrow
  B) A line
  C) A node
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 

Arrows on an AON project network represent:
  A) An activity
  B) Project flow
  C) Dependency
  D) Both B and C are correct
  E) Both A and B are correct
 
 
 

Which of the following is provided by a project network but not by the work breakdown structure?
  A) Dependencies
  B) Sequencing
  C) Interrelationships
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 

Part of a project is to Develop Product Specifications. This is best classified as a(n)
  A) Event
  B) Path
  C) Activity
  D) Node
  E) Milestone
 
 
 

The critical path in a project network is the
  A) Shortest path through the network
  B) Longest path through the network
  C) Network path with the most difficult activities
  D) Network path using the most resources
  E) Network path with the most merge activities
 
 
 

An item on a project network is Design Software Completed. This is best described as a(n)
  A) Event
  B) Path
  C) Activity
  D) Node
  E) Milestone
 
 
 

A sequence of connected, dependent activities is termed a(n)
  A) Critical path
  B) Parallel path
  C) Activity chain
  D) Path
  E) Dependent chain
 
 
 

Which of the following is not one of the basic rules to follow when developing project networks?
  A) An activity cannot begin until all preceding activities have been completed
  B) Each activity must have a unique identification number
  C) Conditional statements are allowed but looping statements are not allowed
  D) An activity identification number must be larger that that of any preceding activities
  E) Networks flow from left to right
 
 
 

________ activities must be completed immediately before a particular activity.
  A) Merge
  B) Burst
  C) Predecessor
  D) Successor
  E) Critical
 
 
 
10 
The forward pass in project network calculations determines the
  A) Earliest time’s activities can begin
  B) Earliest time’s activities can be finished
  C) Duration of the project
  D) Both A and B are correct
  E) A, B, and C are all correct
 
 
 
11 
The backward pass in project network calculations determines the
  A) Latest time’s activities can begin
  B) Earliest time’s activities can be finished
  C) Critical path
  D) Both A and C are correct
  E) A, B, and C are all correct
 
 
 
12 
The amount of time an activity can be delayed and yet not delay the project is termed
  A) Total slack
  B) Free slack
  C) Critical float
  D) Float pad
  E) Slip pad
 
 
 
13 
The laying pipe example in the text illustrates the concept of
  A) Laddering
  B) Hammock activities
  C) Critical path
  D) Concurrent engineering
  E) Forward pass
 
 
 
14 
Typically an activity on a project network represents
  A) A single work package
  B) One or more tasks from a work package
  C) Several work packages
  D) A sub-deliverable
  E) A cost account
 
 
 
15 
Concurrent engineering is a good example of good use of
  A) Start to Start lags
  B) Start to Finish lags
  C) Finish to Finish lags
  D) Finish to Start lags
  E) Any of these could be correct

Need your ASSIGNMENT done? Use our paper writing service to score better and meet your deadline.


Click Here to Make an Order Click Here to Hire a Writer